SECTION 67-1107. Cost to Commonwealth in connection with inspection and coordination of construction of line to be paid by renewable generator  


The actual costs and expenses of the Commonwealth for the inspection or coordination of the construction or installation of any of the distribution facilities of the renewable generator, under the provisions of this chapter, under any permit of the Commonwealth Transportation Board shall be borne by the renewable generator. The sum of the payment required by this section shall be paid to the Department of Transportation within 30 days from the receipt of a progress or final bill from the Department of Transportation.

2009, c. 807 .